Traffic Advisories

The streets or sidewalks listed below are currently impacted by construction work or other closures.

Location Dates Impacts
Wildcat Canyon Road between Park Hills Road and Woodmont Avenue 09/12/22 - 10/14/22

Roadway and slope failure improvements to various locations on Wildcat Canyon Road between Sunset Ln and Woodmont Ave. 

  • Wildcat Canyon Rd in the northbound direction will be closed during entire duration of project (between Park Hills Rd and Woodmont Ave).
  • At certain points of project, traffic on Wildcat Canyon Rd will be closed to all traffic (between Sunset Ln and Woodmont Ave). Southbound traffic on Wildcat Canyon Rd will not be available to through traffic. At these times, only residents between Sunset Ln and Woodmont Ave will be able to drive southbound.
Browning Street from Addison Street to Dwight WayColusa Avenue from North City Limit to Solano AvenueDelaware Street from Acton Street to Sacramento StreetEllsworth Street from Stuart Street to Ashby AvenueFulton Street from Dwight Way to Stuart StreetHeinz Avenue from 7th Street to San Pablo Avenue9th Street from Heinz Avenue to South End near Berkeley BowlStuart Street from Fulton Street to Ellsworth StreetStuart Street from Benvenue Avenue to College AvenueSunset Lane from Grizzly Peak Boulevard to Wildcat Canyon RoadAllston Way from Martin Luther King Jr. Way to Milvia StreetDwight Way at California Street 07/25/22 - 11/01/22

Possible traffic delays, street closures, and/or "No Parking" signs during street pavement rehabilitation.  Access to private driveways may be prohibited during some operations. Emergency vehicle access will be maintained at all times. Learn more about this street rehabilitation project.

Also included is construction of Phase 3 of the Dwight Way/California Street Intersection Project.

North side of Gilman Street near Fourth Street 07/19/22 - 09/30/22

Sidewalk and curb ramp work by Caltrans on the north side of Gilman Street near Fourth Street. Gilman Street will remain open throughout the work. Work will take place mostly from 6:00 a.m. to 5:00 p.m., Monday through Friday, and on some weekends.

A pedestrian detour will be in effect. The closure will accommodate work in preparation for a bicycle track being built as part of the Interstate 80 Gilman Street Interchange Project.

Intersection of Marin Avenue and Spruce StreetIntersection of Marin Avenue and Regal RoadIntersection of Marin Avenue and Euclid AvenueEuclid Avenue from Marin Avenue to Regal RoadIntersection of Marin Avenue and Shattuck AvenueSan Benito Road - #927 to #935High Court - #1107 to #1111Virginia Street at Arch StreetVirginia Street at Spruce Street#1220 Grizzly Peak Boulevard/#2954-2956 Shasta Road 07/18/22 - 10/31/22

Possible traffic delays, street closures, and/or "No Parking" signs during storm drain improvements. Access to private driveways may be prohibited during some operations. Emergency vehicle access will be maintained at all times. Learn more about this storm drain improvement project.

5th Street from Cedar Street to Virginia Street 07/18/22 - 11/01/22

Possible traffic delays and lane closures while PG&E replaces existing electrical facilities. 

Sunset Lane from Woodmont Avenue to Wildcat Canyon Road 07/12/22 - 10/31/22

EBMUD water line replacement. Expect lane closures and traffic delays.

Grayson Street from 7th Street to San Pablo Avenue8th Street from Grayson Street to Heinz Avenue9th Street from Grayson Street to Heinz Avenue10th Street from Grayson Street to Heinz AvenueHeinz Avenue from 8th Street to 10th Street 05/23/22 - 12/20/22

PG&E gas line replacement. Expect lane closures and traffic delays.

Parker Street from Mabel Street to Sacramento StreetActon Street from Dwight Way to Blake StreetDwight Way from Mathews Street to Sacramento StreetBlake Street from Mabel Street to Sacramento Street 05/16/22 - 12/16/22

PG&E gas line replacement. Expect lane closures and traffic delays.

Eunice Street from Spruce Street to Euclid AvenueSpruce Street from Eunice Street to Glen AvenueEunice Street from Walnut Street to Oxford StreetEuclid Avenue from Grizzly Peak Boulevard to Poplar Street 05/09/22 - 09/30/22

Possible traffic delays, street closures, and/or "No Parking" signs during sanitary sewer rehabilitation. Access to private driveways may be prohibited during some operations. Emergency vehicle access will be maintained at all times. No significant interruptions in sewer, water, electric, gas, or phone service are anticipated, though minimizing your water usage during this time is recommended. Learn more about this sewer rehabilitation project.

Portions of Tremont, Eton, Alcatraz, Mystic/Brookside backline, Hazel, Domingo, El Camino, Vicente, Alvarado, Tunnel, Roble and Chabot backline 04/25/22 - 09/30/22

Possible traffic delays, street closures, and/or "No Parking" signs during sanitary sewer rehabilitation. Access to private driveways may be prohibited during some operations. Emergency vehicle access will be maintained at all times. No significant interruptions in sewer, water, electric, gas, or phone service are anticipated, though minimizing your water usage during this time is recommended. Learn more about this sewer rehabilitation project.

Shattuck Avenue from Derby Street to Allston WayShattuck Avenue from University Avenue to Vine StreetAddison Street from Shattuck Avenue to Kala Bagai WayUniversity Avenue from Kala Bagai Way to Shattuck Avenue 04/15/22 - 10/15/22

Possible traffic delays, street closures, and/or "No Parking" signs during sanitary sewer rehabilitation. Access to private driveways may be prohibited during some operations. Emergency vehicle access will be maintained at all times. No significant interruptions in sewer, water, electric, gas, or phone service are anticipated, though minimizing your water usage during this time is recommended.

Dwight Way near Fernwald Rd and on UC Berkeley’s Clark Kerr CampusDwight Way from Prospect St to Piedmont AvePiedmont Ave from Dwight Way to Forest AveForest Ave from Piedmont Ave to Claremont BlvdAlong Claremont Blvd and Garber St to Tanglewood RdTanglewood Rd from Garber St to Claremont AveClaremont Ave between Tanglewood Rd and 7287 Claremont Ave 01/10/22 - 06/30/23

EBMUD pipeline replacement work will take place in locations in Berkeley and Oakland.

Typical work hours are 7 a.m. to 7 p.m. with restricted work hours near Emerson Elementary School, on UC Berkeley’s Clark Kerr Campus and along busy intersections and roadways.