Type:
Facility
Status:
Design
Project Location
1326 Allston Way
WHAT'S HAPPENING
This is a Measure T1 Phase 2 project.
The Corporation Yard is home for hundreds of employees that help provide services that help make the City a better and safer place for those who live, visit, or commute in it. This project consists of various upgrades to multiple facilities within the Corporation Yard, including paving, site drainage, roof repairs, electrical and mechanical upgrades, and renovations to the restrooms, training, locker rooms. The Green Room upgrade is in the final design stage and the next deliverable will be a permit set of drawings, specifications, and cost estimate. The H building is in the 60% design stage. The Green Building is in the permitting phase.
Images

Corporation Yard
Corporation Yard
Funding Source
Project Team