Project Location
400-408 Gilman St, Berkeley, CA 94710
WHAT'S HAPPENING
This is a Measure T1 Phase 2 project.
The Tom Bates Regional Sports Complex is considered to be the most highly used fields in the region. The recently replaced artificial fields provide up to 300,000 players and serves approximately 19,000 youth and adults annually. The complex does not have a permanent meeting space or restroom at the site. The finalized space planning phase consists of a restroom, meeting room, and a storage area, with a priority on ease of access from the fields, minimal impact to parking, and good security.
This project is currently in 30% design. A design team has been retained to begin final design, prepare construction documents and obtain any applicable permits. Construction is anticipated to start in 2025.
Documents
Funding Source
Project Team