Project Location
Telegraph Ave @ Channing Way
San Pablo/University Ave
Adeline/Alcatraz Ave
WHAT'S HAPPENING
This is a Measure T1 Phase 2 project.
In 2018, the City conducted a Citywide Restroom study. Upon completion of the study in 2020, the team developed a plan and based on those recommendations, three outdoor public restrooms will be installed at the above locations.
Telegraph-Channing
The City completed a survey of the site upon which the restroom will be constructed, including utilities at the site, and design of the restroom in Winter 2023. The site survey identified three PG&E gas service lines at the site, which PG&E said were inactive (abandoned). The City selected a contractor and began seeking permits for the construction, including from PG&E and EBMUD. Upon the request for a permit, PG&E informed the City that one of the three gas service lines at the site was actually active and would need to be rerouted to circumvent the new restroom. PG&E designs such rerouting internally, a process that typically takes eight months. So, the permitting and start of construction has been delayed eight months. Whereas the City expected the restroom to be open in fall 2023, the City now expects the construction to start in April/May 2024, lasting approximately 8 months.
Alcatraz-Adeline & San Pablo-University
The design of these two bathrooms is almost complete. For better pricing, both will be bid as one package. The final design and permits are expected by June, 2024. The next steps will be Public Bid (June/July, 2024), Council Approval (October, 2024), Contract (December, 2024), Begin Construction (Early 2025), End Construction (Mid/late 2025).
Past Events
Funding Source
Project Team