Type:
Street
Status:
Design
Project Location
Hopkins Street from San Pablo Avenue to Sutter Street
WHAT'S HAPPENING
This is a Measure T1 Phase 2 project.
This project is currently in the design phase. Final design, subject to Council approval of conceptual plans of Hopkins Street west of Gilman Street and review of parking study for the area between McGee Avenue and Gilman Street, is scheduled for early 2023. Based on the current scope and cost estimate, additional funding of approximately $3 million is required for the project. The current schedule has the project bidding in the spring of 2023, council award of contract in the summer of 2023, and start of construction in the Fall of 2023.