Project Location
1730 Oregon Street, Berkeley, CA 94703
WHAT'S HAPPENING
This is a Measure T1 Phase 1 and Phase 2 project.
Phase 2 improvements to the park are ongoing. Phase 1 improvements included reconstruction of the tennis courts, and renovation of the basketball courts and public restroom, completed in 2017. Phase 2 improvements include: renovation of turf and infield area; landscaping and irrigation improvements; netting and fence improvements; the demolition and reconstruction of the Age 2-5 playground and Age 5-12 playground; accessibility improvements throughout the project site; renovation of the picnic area; drainage improvements; and various other related site improvements.
Construction commenced in May 2023 and is ongoing. The playgrounds have been delivered to the site and are being assembled, new backstops and accessibility upgrades have been completed with new chain link fencing, new irrigation has been installed and is being tested, and new sod has been placed and is being established. Upcoming work involves netting post installation and infield grading.
The playground area is expected to be completed by January 2024, with the field following in March 2024. During this improvement process there will be impacts to the field, play and picnic areas.
Past Events
-
Grove Park Community Meeting
November 7, 2019 1 DocumentsDocument
- Grove Park Community Meeting (790.92 KB) (790.92 KB)
-
Grove Park Field and Playground Renovation Project Community Meeting, June 2021
June 23, 2021 3 DocumentsDocumentDocumentDocument
-
Grove Park Field and Playground Renovation Project Community Meeting, September 2021
September 22, 2021 3 DocumentsDocumentDocumentDocument
Documents
- Grove Park Project Sign.pdf (434.65 KB) (434.65 KB)
Project Team